Status of Change Requests
| CR NUMBER | CHANGE REQUEST | DOCUMENT ID | SECTION ID | UNIQUE # | STATUS |
|---|---|---|---|---|---|
| 1 | Add better description | F-SP-001 | 5.5 | FSP001-0052-01 | Approved |
| 2 | Add identifiable, searchable | F-SP-001 | 5.5 | FSP 001-0053-01 | Implementation Under Review |
| 3 | Include list of acceptable model formats for exchange purposes | F-SP-001 | 5.5 | NA | Implementation Under Review |
| 4 | Include requirements for what needs to be specified to the suppliers of packaged units | F-SP-001 | 5.5 | NA | Implementation Under Review |
| 5 | Update the Terms table with: - Add terms for: Plant, Process Plant, Plant Section, Equipment, Specified Equipment, Physical Equipment, Component - Align terms: Tag, Object Verify across the Specification document the correct use of the terms | F-SP-001 | 3.2 | Implementation Under Review | |
| 6 | The requirement should also include non-tagged items that appear on the P&ID. | F-SP-001 | 6.4.2h | Implementation Under Review | |
| 7 | The requirement reads: All GA3D models shall not contain elements intended for installation only (i.e. lifting slings, transportation supports). | F-SP-001 | 6.5.7g | FSP001-0143-01 | Implementation Under Review |
| 8 | The requirement reads: All GA3D models shall not contain any temporary elements or volumes. | F-SP-001 | 6.5.7j | FSP001-0146-01 | Implementation Under Review |
| 9 | Proposed Text: Each 3D datum point shall be related to PCS and real-world planar coordinate system indicated by Company, i.e. UTM, SPCS or EPSG:3857. Plant elevation reference used like MSL or GD elevation. | F-SP-001 | 5.1.1 | FSP001-0003-02 | Rejected |
| 10 | Proposed Text: The Contractor shall document each 3D datum point indicated with reference to real-world and local Plant Coordinate Systems. Easting and Northing shall be used with reference to real-world planar coordinates . East and North with reference to local plant coordinate system (PCS). | F-SP-001 | 5.1.1 | FSP001-0004-02 | Rejected |
| 11 | Proposed Text: Users shall be able to identify the objects within specific area codes. | F-SP-001 | 5.3 | FSP001-0020-02 | Implementation Under Review |
| 12 | Proposed Text: Hierarchy shall be aligned with global workshare configuration. | F-SP-001 | 5.3 | Rejected | |
| 13 | Suggest stakeholder chart is replaced by two RACI matrices, one Greenfield and one Brownfield | F-GU-002 | 4.3 | Recommendation Provided | |
| 14 | Suggest add a section for Operational use cases, e.g. remote working, operator training, maintenance/turnaround planning, brownfield modifications, etc. | F-GU-002 | N/A | Recommendation Provided | |
| 15 | include reference to company/industry standards to be followed: 3D model review requirements. Milestones, content, applicable standards, procedures, follow up to comments, attributed data included. | F-CL-002 | Line 36 | Published | |
| 16 | Providen clarity the type of applications used, e.g. Data-centric, rule-driven native 3D model mapped to catalogues and specifications. | F-SP-001 | 6.2 | FSP001-0045-02 | Rejected |
| 17 | Provide clarity on the nature of the geometry. Suggested text: The envelope of an object modelled with a generic geometry shall represent the maximum dimension of that object to allow for clash checking. The generic geometry can be built with one or more 3D primitive shapes for a simplified representation. | F-SP-001 | 6.3 | FSP001-0048-01 | Rejected |
| 18 | Probably this needs to be discussed to provide clarity on what is expected. That may be different on the natire of the application used. Text proposed to add to specification: Vendors shall provide 3D Models that are simplified and de-featured so they can be easily imported into the 3D design environment. Acceptable 3D CAD formats are: Preference on formats files from original authoring tools like .STP, .STEP, .SAT, .DWG, .DGN or .IFC (Other formats will require Company / EPC approval). If vendor 3D models are to be delivered in 3D CAD system formats like PDS, PDMS, Smart3D, E3D or CADWorx, the vendor should contact company / contractor for details of the dataset format. Maximum file Size <= 20 MB to ensure optimum 3D performance for imported or inserted 3D models. Larger sizes shall be approved by Company / EPC. 3D Model level of detail and size will be fully approved after the first delivery. | F-SP-001 | 6.5.11, 6.5.12 | Review Pending | |
| 19 | Clarity on Clash Free meaning. Suggested text: The final handed-over 3D model shall be clash-free. Clash-free means that all clashes have been reviewed, resolved or approved. Unapproved clash status is not acceptable for final hand-over. | F-SP-001 | 8.3 | FSP001-0064-01 | Implementation Under Review |
| 20 | The column Model Requirements on the 3D Model Deliverables tab should be aligned with the FL3DMS Content Requirement Matrix and make the correct references. This might also lead to additions to the the Content Requirement Matrix | F-SP-003 | Registered | ||
| 21 | Review the the 'Not mapped to NORSOK' requirements and decide to which NORSOK requirement they map to, or map them to No requirement in NORSOK option | F-CR-001 | Implementation Under Review | ||
| 22 | 1. [FSP001-xxxx-01] Catalogues and specifications objects shall not be removed after implementation, even if not referenced by the design model. | F-SP-001 | 6.4.2 | N/A | Implementation Under Review |
| 23 | 1. All catalogue, specification and properties elements shall contain a Contractor prefix or suffix to avoid conflict occurring with other catalogue and specification elements that are used within the model. 2. Contractor code shall be agreed upon with the Company to avoid duplication. | F-SP-001 | TBA | N/A | Implementation Under Review |
| 24 | Add list of reference documents, e.g. Content matrix, lifecycle guide, data guide, etc. | F-SP-001 | 2 | N/A | Being Implemented |
| 25 | Delete the following abbreviations: NPD, PO, SDI, SIRL | F-SP-001 | 3.1 | N/A | Implementation Under Review |
| 26 | Change 'Top Tag' to 'Main Tag' | F-SP-001 | 3.2 | N/A | Implementation Under Review |
| 27 | Review wording - UoM requirements does not just apply to NPD and dimensions. Change it to: Contractor shall provide details of the units of measure used for the 3D Model configuration. | F-SP-001 | 4 | FSP001-0193-01 | Implementation Under Review |
| 28 | Change 'items' to 'objects' | F-SP-001 | 5.2.2 | FSP001-0010-02 | Implementation Under Review |
| 29 | Change 'item' to 'object' | F-SP-001 | 5.2.2 | FSP001-0011-02 | Implementation Under Review |
| 30 | Change 'items' to 'objects' | F-SP-001 | 5.2.2 | FSP001-0013-02 | Implementation Under Review |
| 31 | Suggest this text is moved under header 5.5 and Introduction deleted | F-SP-001 | 5.5.1 | N/A | Implementation Under Review |
| 32 | Delete this clause | F-SP-001 | 6.2 c | FSP001-0046-02 | Implementation Under Review |
| 33 | Handover is section 8.4 - this section should be "As-built Requirements" - please review both sections and clarify content for each. | F-SP-001 | 6.4 | Title | Under Review |
| 34 | Change title to: "Selection of As-built Requirements" | F-SP-001 | 6.4.1 | Title and text | Implementation Under Review |
| 35 | Suggest this section is retitled "3D Model As-built Requirements" | F-SP-001 | 6.4.2 | Title | Implementation Under Review |
| 36 | Reword as: "The as-built 3D Model content shall be consistent with the as-built deliverables as used for fabrication and construction." | F-SP-001 | 6.4.2a | FSP001-0104-01 | Implementation Under Review |
| 37 | Move to Handover section. This relates to study or FEED handover and is not relevant to as-built | F-SP-001 | 6.4.2d | FSP001-0107-01 | Being Implemented |
| 38 | Delete this clause | F-SP-001 | 6.4.2e | FSP001-0108-01 | Implementation Under Review |
| 39 | Review text as this clause is similar to clause e in the same section | F-SP-001 | 6.4.2f | FSP001-0109-01 | Implementation Under Review |
| 40 | What constitutes "unusually large"? | F-SP-001 | 6.4.2g | FSP001-0110-01 | Being Implemented |
| 41 | Reword as: 'The 3D Model shall be as-built in accordance with the "Red-Line Mark-Up" comments from engineering deliverables and mechanical completions checks.' | F-SP-001 | 6.4.2i | FSP001-0112-01 | Review Pending |
| 42 | Reword as: "The Contractor shall utilise reality capture technology to check the as-built 3D Model content is aligned with the physical status of the plant." | F-SP-001 | 6.4.2j | FSP001-0113-01 | Review Pending |
| 43 | Replace "top tag" with "main tag" | F-SP-001 | 6.5.1a & d 6.5.4a | FSP001-0115-01 FSP001-0130-01 FSP001-0131-01 | Implementation Under Review |
| 44 | Replace "Packet" with "Package" | F-SP-001 | 6.5.4a | FSP001-0130-01 | Implementation Under Review |
| 45 | Reword as: 'Neutral format GA3D vendor model file shall be split into discipline specific models, unless otherwise agreed with the Purchaser.' | F-SP-001 | 6.5.4b | FSP001-0132-01 | Review Pending |
| 46 | Delete this clause | F-SP-001 | 6.5.4c | FSP001-0133-01 | Review Pending |
| 47 | Replace "if not otherwise agreed with the purchaser." with "unless otherwise agreed with the Purchaser." | F-SP-001 | 6.5.5a | FSP001-0134-01 | Review Pending |
| 48 | Replace "if not otherwise agreed with the purchaser." with "unless otherwise agreed with the Purchaser." | F-SP-001 | 6.5.5b | FSP001-0135-01 | Review Pending |
| 49 | Reword as: "A GA3D model of the vendors scope of work in a review model format, agreed with Purchaser, without expiry dates or any password protection." | F-SP-001 | 6.5.5c | FSP001-0136-01 | Review Pending |
| 50 | Replace "Source" with "native" | F-SP-001 | 6.5.6c | FSP001-0139-01 | Review Pending |
| 51 | Replace "Skid/Package" with "Module/Skid" | F-SP-001 | 6.5.8b | FSP001-0193-01 | Review Pending |
| 52 | Refer Main tag box: Replace "Skid tag" with "Module tag" | F-SP-001 | 6.5.8e | FSP001-0158-01 | Review Pending |
| 53 | Replace "top tags (multiple GA Packets)" with "Main tags (multiple GA packages)" | F-SP-001 | 6.5.9 | FSP001-0159-01 | Review Pending |
| 54 | Reword note so that it makes sense | F-SP-001 | 6.5.9 | FSP001-0159-01 | Review Pending |
| 55 | Replace text with "The vendor model neutral file maximum size limit shall be agreed with the Purchaser." | F-SP-001 | 6.5.10a | FSP001-0160-01 | Review Pending |
| 56 | Replace "more files" with "multiple files, reference section 6.5.4" | F-SP-001 | 6.5.10b | FSP001-0161-01 | Review Pending |
| 57 | Delete this clause | F-SP-001 | 6.5.10c | FSP001-0162-01 | Review Pending |
| 58 | Suggest reword to clarify requirement as it currently applies to the information management system. For example: "3D model attributed data and links shall be aligned with the master information management system." | F-SP-001 | 6.7c | FSP001-0060-01 | Review Pending |
| 59 | Suggest these two clauses are combined into one, delete a10 and replace a3 with: "That will be in a condition where it will open, function and be editable with full intelligence on the same standard software and version the Contractor used to build the 3D model without further development by Company. This includes reference catalogues and specifications and any configurable files required to fully modify and edit the model." | F-SP-001 | 8.4 a3 & a10 | FSP001-0074-01 | Review Pending |
| 60 | Suggest to reword to avoid duplication with 8.4.1 b2. For example: "With all detailed documentation related to the 3D model development." | F-SP-001 | 8.4 a4 | FSP001-0071-01 | Being Implemented |
| 61 | Delete this clause | F-SP-001 | 8.4 a5 | FSP001-0072-02 | Being Implemented |
| 62 | Replace text "section 5.5.12" with "the FL3DMS Content Requirement Matrix F-CR-001" | F-SP-001 | 8.4 a7 | FSP001-0074-01 | Being Implemented |
| 63 | Change F-SP-003 reference number to F-SP-004 | F-SP-001 | FSP001-0059-03 The Attributes in F-SP-003 FL3DMS Data Model shall be set when a new object is created. | Implementation Under Review | |
| 64 | par. 6.7 should refer to F-SP-004 to F-SP-003 | F-SP-001 | 6.7 | FSP001-0107-01 The contractor shall ensure that all application-specific 3D Model data delivered is consistent with corresponding information or engineering deliverables generated from the 3D Model, as set out in F-SP-003 FL3DMS 3D Model Deliverables List. | Under Review |
| 65 | add a description what the FL3DMS unique IDs at the beginning of each requirement are and how the numbering works: new number or just a revision update. | F-SP-001 | 1.2 Content | Review Pending | |
| 66 | Align the terminology | F-SP-003 and F-SP-004 | FSP001-0059-03 references 'Attributes' in F-SP-004. F-SP-004 talks about 'Properties' | Review Pending | |
| 67 | Consider to specify export formats for datasets, as an initial start for a generic data model. An initial spec could be like: 1. The 3D Model shall export a list of “3D spatial components” with all properties as defined in F-SP-004 in a comma-separated file with the column headers being the FL3DMS Unique ID with the name “FL3DMS 3D Spatial Components.csv” 2. The 3D Model shall export in a comma-separated file with column headers being the CFIHOS unique codes with the name CFIHOS-00000028.csv the tags as modelled in the 3D Model. 3. The 3D Model shall export in a comma-separated file with column headers being the CFIHOS unique codes with the name CFIHOS-00000015.csv the tag properties as modelled in the 3D Model. 4. The 3D Model shall export in a comma-separated file with column headers being the CFIHOS unique codes with the name CFIHOS-00000012.csv the equipment as modelled in the 3D Model. 5. The 3D Model shall export in a comma-separated file with column headers being the CFIHOS unique codes with the name CFIHOS-00000013.csv the equipment properties as modelled in the 3D Model. 6. The 3D Model shall export in a comma-separated file with column headers being the CFIHOS unique codes with the name CFIHOS-00000038.csv the tag physical connections as modelled in the 3D Model. 7. The 3D Model shall export in a comma-separated files with column headers being the CFIHOS unique codes, for the created deliverables: -document master data named CFIHOS-00000022.csv -document revision data named CFIHOS-00000035.csv -document revision site reference named CFIHOS-00000078.csv -document revision plant reference named CFIHOS-00000079.csv -document revision process unit reference named CFIHOS-00000080.csv -document revision plant area reference named CFIHOS-00000081.csv -document revision tag reference named CFIHOS-00000082.csv -document revision equipment reference named CFIHOS-00000083.csv -document revision project reference named CFIHOS-00000087.csv | F-SP-001 | Review Pending | ||
| 68 | review the definition of Vendor Package / Skid: is: Vendor Package / Skid A vendor package or skid is an assembly of more than one equipment, tag or product and is delivered as one or more units, normally designed and delivered by the contractor’s vendor of the skid. Proposed: A vendor package or skid is an assembly of more than one equipment and is delivered as one or more units, normally designed and delivered by the contractor’s vendor of the skid. | F-SP-001 | 3.2 Terms & Definitions | Review Pending | |
| 69 | replace “the operating asset owner” with “Company” | F-SP-001 | 8.4 | FSP001-0194-01 The 3D Model handed over to the operating asset owner shall be in a condition where it will open, function, and be editable with full intelligence in the same out-of-the-box application version from the same software vendor that the contractor used to design the 3D model. This includes reference catalogue and specifications, and any configurable files required to fully modify and edit the 3D model. | Decision Pending |
| 70 | Add a as-built requirement for the Catalogue where various vendors deliver the same item, with still difference in the actual operator size. See the paragraph in the draft Cats & Specs guide: 5.4 As-building. | F-SP-001 | 6.4.2 As-building | N/A | Review Pending |
| 71 | USPI should define a limited, testable interface connecting an AAS asset identifier to the corresponding FL3DMS object and lifecycle evidence, with the authoritative source for each property made clear. No new FL3DMS AAS submodel or wider digital-twin architecture is justified by this event alone. | F-SP-004 | n/a | N/A | Registered |